​​​S.No. Name of the Projects​
Length (in kms) Anticipated Cost (in ₹ crore)
NEW LINE
1 Haridaspur - Paradeep New Line 82.00 1,845
2 Angul - Sukinda New Line 99.00 1,2023
3 Mau-Ghazipur-Tarighat New Line 51.00 1,7660
4 ​Obulavaripalle - Krishnapattnam New Line 122.00 1,825
5 Dallirajhara - Rowghat New Line 95.00 632
DOUBLING
6 Vizianagaram -Samabalpur 3rd Line 265.00 2,336
7 Mathura-Jhansi 3rd Line 274.00 3,678
8 Vijaywada - Gudivada - Bhimavaram - Narasapur, Gudiva Da - Machilipatnam & Bhimavaram - Nidadavolu Doubling With Re 221.00 1,504
9 Hospet - Tinaighat - Vasco-Da-Gama Doubling 307.41 2,127
10 Palanpur - Samakhiali Doubling 247.73 1,549
GAUGE CONVERSION
11 Lucknow- Pilibhit Via Sitapur, Lakhimpur Gc 262.76 927
12 Ahmedabad - Botad Gauge Conversion 170.48v 976
13 Dhasa - Jetalsar Gauge Conversion 104.44 644
RAILWAY ELECTRIFICATION
14 Pune - Guntakal Rly Elect. 641.37 801
15 Raninagar Jalpaigudi -New Bongigaon - Guwahati (Incl) Re-382 Km ( Part Of Barauni - Katihar - Guwahati Incl. Katihar - Barsoi ( 836 Km) Re 221.00 656
METROPOLITAN TRANSPORTPROJECTS
16 Baranagar - Barrackpore & Dakshineswar - Construction Of Metro Railway Line 14.50 2,734
17 Dum Dum Airport - New Garia Via Rajerhat Construction Of Metro Railway 32.00 4,260
18 Joka - Binoy Badal Dinesh Bagh Via Majerhat - Construction Of Metro Railway 16.72 4,939
19 Naupara(Ex.) - Baranagar Extension Of Dumdum - Baranagar Metro Rail Link v 2.60 465
20 Multi-Modal Transport System (Mmts) – Phase-II 101.05 817
WORKSHOP
21 Vadlapudi – Wagon Poh Workshop Of 200 Nos Capacity Near Duvvada Station v ​Nil 214
22 Aunrihar – Demu Shed Nil 1,23
23 Other Specific Works Nil
24 Moula Ali – Setting Up Of Indian Railway Institute Of Finance Management Nil 65
25 Madar-Palanpur-Removing Of Psr (Km 589/1 To 590/1) Nil 10
OTHERS
Road Over Bridge
26 Srirangam – Tiruchacirapalli Town – 4 Lane Rob In Lieu Of 2 – Lane Bridge No. 380-A Nil 2
Railway Safety Works
27 Dhasa-Jetalsar-Subways In Lieu Of Level Crossing-35 Nos. Nil 9
28 Sabarmati-Botad-Subways In Lieu Of Level Crossings-23 Nos. Nil 6
29 Sabarmati-Botad-Subways In Lieu Of Lcs- 14 Nos. Nil 2
Traffic Facility Works
30 Paman-Bhimsen – New B-Class Station Nil 7
31 Jhansi-Garhmau, Orai-Ata, Ata-Kalpi & Pokhrayan-Lalpur – Splitting Of Longer Block Sections Nil 3
32 New Crossing Station Between Umdanagar-Timmarpur Stations Of Secunderabad-Mahabubnagar Section Nil 2
Final Location Survey
33 Final Location Survey For New Line Connectivity To Char Dham 327.00 1,21
​​​