RVNL is presently having 46 projects broadly classified under two heads as under:
- Strengthening of Golden Quadrilateral and Diagonals - 26
- Provision of Port connectivity and corridors to hinterland - 20
| Doubling | = 1811 Km |
| Gauge Conversion | = 1585 Km |
| New Line | = 493 Km |
| RE | = 1906Km |
| TOTAL | = 5795 Km |
Upto 31.3.2007, RVNL has completed 10 projects/project sections covering 155 Kms. of new lines, 795 Kms. of gauge conversion, 276 Kms. of doubling, and 954 Kms. of Railway Electrification. This is approximately 37% of the total length of projects assigned to RVNL.
RVNL has achieved an impressive growth in its business of project execution. The expenditure on account of project works (inclusive of expenditure by SPVs) has increased from Rs.843.35 Cr. to Rs.1236.24 Cr. registering a growth of 46.59% during the financial year 2006-07.
During the next financial year 2008-09, construction of 640 Kms BG Line and 100 Km of Railway Electrification are likely to be completed.